California First National Bank v. Boh Bros. Construction Co., L.L.C.

United States District Court, E.D. Louisiana

February 13, 2019

CALIFORNIA FIRST NATIONAL BANK
v.
BOH BROS. CONSTRUCTION CO., L.L.C.

         SECTION: “J” (5)

          ORDER AND REASONS

          CARL J. BARBIER UNITED STATES DISTRICT JUDGE.

         Before the Court is a Motion for Summary Judgment (Rec. Doc. 36) filed by California First National Bank (“CalFirst”). Boh Bros. Construction Co. (“Boh Bros.” or “Boh”) filed an opposition to the motion (Rec. Doc. 43), to which CalFirst replied. (Rec. Doc. 47). Considering the motion, the memoranda, the record, and the law, the Court finds the motion should be GRANTED.

         FACTS AND PROCEDURAL BACKGROUND

         This litigation arises out of two unpaid invoices for labor and materials Boh Bros. provided as part of an expansion project at Noranda Alumina, LLC's (“Noranda”) plant in Gramercy, Louisiana (“the Project”). Noranda filed for bankruptcy and never satisfied the invoices. Boh Bros. claims that CalFirst, as Noranda's lender, became the owner of the Project and that Boh Bros. and CalFirst entered into a contract that made CalFirst liable to pay the unpaid invoices.

         Boh Bros. executed a contract (the “Construction Contract”) with Noranda on September 17, 2015, in which Boh Bros. agreed to provide labor, equipment, and materials necessary for fabrication and installation of a part of the Project.[1] Boh Bros. procured a significant amount of the materials for the Project before execution of the Construction Contract.[2] Accordingly, Boh Bros. promptly issued two invoices to Noranda for its costs: Pay Application No.1 accounted for costs through September 1, 2015 amounting to $1, 063, 200; Pay Application No. 2 covered costs through September 15, 2015 amounting to $1, 329, 000.[3] These invoices were dated September 17, 2015.[4]

         CalFirst provided the financing for the project pursuant to Lease Agreement Order No.ML-00269, Lease Schedule No. 1 (“Lease Agreement, ” “Lease Schedule, ” respectively), and various subsidiary agreements entered into between CalFirst and Noranda.[5] The financial backing for the Project was structured in the form of a lease-what the parties both refer to as a form of “disguised financing.”[6] Per the Lease Agreement, CalFirst, as “lessor, ” agreed to “lease to Lessee [Noranda] the hardware, software, equipment” and the associated production costs.[7] In a letter agreement, CalFirst agreed it would “advance[e] funds to supplier(s) on behalf of Lessee [Noranda].”[8] According to the Lease Agreement, “Lessor [CalFirst] at all times retains ownership, title and/or control over Lessee's [Noranda's] right to use the Property in accordance with the terms of the Lease.”[9] However, the Lease Agreement specifically states that CalFirst “will not disburse payment to Suppliers . . . [u]nless and until Lessee provides . . . written authorization.”[10] As additional security, the Lease Schedule required Noranda to arrange for a letter of credit from a bank acceptable to CalFirst that was equal to 90% of the total disbursements to suppliers.[11]

         Noranda advised Boh Bros. of the financing structure shortly after the Construction Agreement was executed.[12] In an e-mail exchange between John Sanchez at Noranda and Kyle Alexander at Boh Bros., Sanchez instructed that invoices should be marked as “Sold to: California First National Bank” and “Ship to: Noranda Alumina, LLC.”[13] Karen Brown, a lease administrator for CalFirst and Boh's point of contact at the bank, confirmed this instruction with Mary Hebert at Boh Bros via e-mail, noting that Boh Bros. should forward invoices directly to Noranda for their review.[14] Boh Bros. sent Pay Apps Nos. 1 and 2 to Noranda on September 25, 2015.[15] Despite the labeling instructions, Boh Bros. did not use the “Sold to” indication on the invoices.[16] Instead, because of a limitation in Boh's accounting software, Boh Bros. identified CalFirst as “Customer” on the forms with CalFirst's approval.[17] After Noranda approved the invoices, CalFirst paid them in the aggregate amount of $1, 196, 100.00 on October 15, 2015.[18]

         On October 6, 2015-before CalFirst paid Pay Apps. Nos. 1 and 2-CalFirst filed a claim for a declaratory judgment against Noranda in the Superior Court of California, Orange County. CalFirst sought a judgment stating it did not need to make further payments to suppliers.[19] The suit was voluntarily dismissed after CalFirst and Noranda agreed that that CalFirst would advance payments to suppliers of up to $5, 000, 000.00, including disbursements already made.[20] For disbursements beyond this $5 million mark, Noranda was required to obtain a new letter of credit securing 90% of the requested amount plus the total prior disbursements by CalFirst.[21]

         While the first two invoices were pending payment, on October 12, 2015, Boh Bros. mobilized to the site to begin construction on the project.[22] For its subsequent work on the Project Boh Bros. submitted Pay App. No. 3, dated November 6, 2015, for $384, 473.25 and Pay App. No. 4, dated December 9, 2015, for $134, 703.00 to CalFirst, with CalFirst designated as “customer.”[23] According to the terms of the Construction Contract, payment was due 60 days from the date of the invoice.[24] Although Noranda obtained an increased letter of credit from Bank of America, Noranda, “with the consent of CalFirst, hand-picked the suppliers it wanted paid.”[25] Boh Bros. was not among the suppliers Noranda chose to pay. Noranda never approved the third and fourth invoices, and CalFirst never paid them.[26]

         Noranda filed a petition for relief in the U.S. Bankruptcy Court for the Eastern District of Missouri on Feb. 8, 2016. CalFirst then filed an adversary proceeding on March 23, 2016, seeking a declaratory judgement to determine the claims against Noranda and Boh. On March 31, 2016, Boh filed a lawsuit against CalFirst asserting claims for breach of contract and detrimental reliance in this Court. This suit was transferred to the bankruptcy court as an adversary proceeding. The bankruptcy court approved a global settlement (including the settlement of Boh's claims against Noranda for unpaid invoices, and CalFirst's claims against Noranda for breach of the Financing with CalFirst) and the bankruptcy was dismissed. On Nov. 23, 2016, the bankruptcy court dismissed one of the adversary proceedings and transferred the declaratory judgment proceeding to this Court. On April 28, 2017, Boh. Bros. filed its answer and counterclaims.[27] This Court dismissed Boh's negligent misrepresentation counterclaim pursuant to 12(b)(6) but allowed the breach of contract and detrimental reliance claims to go forward.[28] CalFirst then filed the instant motion for summary judgment.

         PARTIES' ARGUMENTS

         Boh Bros. advances two avenues of relief. First, Boh Bros. argues that CalFirst is liable for breach of contract. This claim requires the Court to accept several layered propositions. First, that CalFirst is the owner of the Project by virtue of Noranda and CalFirst's financing agreement. Second, that a “Supply Contract” was formed by the communications between Hebert and Brown; specifically, their e-mails regarding CalFirst's instruction that the invoices be marked as “Sold to [CalFirst].” Third, that CalFirst breached its implicit agreement by not paying the third and fourth invoices.

         CalFirst argues that summary judgment is appropriate because each proposition fails. First, CalFirst disputes that the financing arrangement was a “true lease.”[29] Rather, the arrangement was “disguised financing, ” whereby the agreement-although couched in the terms of a lease-was actually a loan secured by a security interest in the Project. This is proved by the fact that Noranda would own the property in exchange for a nominal purchase price of $1 upon completing the required payment schedule.

         Second, CalFirst opines that there has never been a contract between CalFirst and Boh Bros. Boh's position is that the Lease Agreement required a “Supply Contract.” To satisfy this requirement, Brown entered CalFirst into a “Supply Contract” with Boh Bros. This contractual relationship was formed, says Boh Bros., when Hebert asked Brown whether CalFirst or Noranda was paying the invoices. When Brown responded that Boh Bros. should use a “Sold to California First National Bank” designation but send the invoices to Noranda first for approval, the “Supply Contract” was formed, and CalFirst became liable to Boh Bros. for the Project invoices, Boh Bros. argues.[30] CalFirst, attacks this argument on multiple fronts, arguing that there was no intent on either side that a contract be formed, and that even assuming there was, Brown lacked actual or apparent authority to enter CalFirst into the alleged “Supply Contract.”

         Third, CalFirst argues that even assuming all its other arguments fail, summary judgment is warranted because CalFirst met the terms of the alleged “Supply Contract.”[31] Hebert, Boh's representative said to have entered into the “Supply Contract” on Boh's behalf, testified the terms were that “CalFirst was going to be paying the invoices on behalf of Noranda . . . after Noranda approved them.”[32]CalFirst, argues it paid for the first two invoices, which were approved by Noranda, but did not pay Pay Apps. Nos. 3 and 4 because they lacked the required approval from Noranda. Citing the testimony of Brown, Boh Bros. argues that CalFirst did not send acceptance certificates to Noranda-a step required to set the approval process in motion.[33] CalFirst counters by quoting Brown, who states the actual procedure was for Noranda to let CalFirst know which invoices it wanted to approve, and then CalFirst would fill out and return an acceptance certificate.[34]

         Boh's second cause of action is for detrimental reliance. Boh claims it would not have mobilized to the site and continued construction if it were not for CalFirst's representations that it would pay the invoices.[35] CalFirst argues that any representation it made could not have resulted in Boh changing its position, because Boh Bros. was bound by its contract to continue working on the job until Noranda was in default.

         STANDARD OF LAW

         Summary judgment is appropriate when “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986) (citing Fed.R.Civ.P. 56); Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994). When assessing whether a dispute as to any material fact exists, a court considers “all of the evidence in the record but refrains from making credibility determinations or weighing the evidence.” Delta & Pine Land Co. v. Nationwide Agribusiness Ins. Co., 530 F.3d 395, 398 (5th Cir. 2008). All reasonable inferences are drawn in favor of the nonmoving party, but a party cannot defeat summary judgment with conclusory allegations or unsubstantiated assertions. Little, 37 F.3d at 1075. A court ultimately must be satisfied that “a reasonable jury could not return a verdict for the nonmoving party.” Delta, 530 F.3d at 399.

         If the dispositive issue is one on which the moving party will bear the burden of proof at trial, the moving party “must come forward with evidence which would ‘entitle it to a directed verdict if the evidence went uncontroverted at trial.'” Int'l Shortstop, Inc. v. Rally's, Inc., 939 F.2d 1257, 1264-65 (5th Cir. 1991). The nonmoving party can then defeat the motion by either countering with sufficient evidence of its own, or “showing that the moving party's evidence is so sheer that it may not persuade the reasonable fact-finder to return a verdict in favor of the moving party.” Id. at 1265.

         If the dispositive issue is one on which the nonmoving party will bear the burden of proof at trial, the moving party may satisfy its burden by merely pointing out that the evidence in the record is insufficient with respect to an essential element of the nonmoving party's claim. See Celotex, 477 U.S. at 325. The burden then shifts to the nonmoving party, who must, by submitting or referring to evidence, set out specific facts showing that a genuine issue exists. See Id. at 324. The nonmovant may not rest upon the pleadings but must identify specific facts that establish a genuine issue for trial. See, e.g., id. at 325, Little, 37 F.3d at 1075. In a non-jury case such as this one, the Court “at the summary judgment stage . . . has the limited discretion to decide that the same evidence, presented to him or her as trier of fact in a plenary trial, could not possibly lead to a different result.” Lyles v. Medtronic Sofamor Danek, USA, Inc., 871 F.3d 305, 311 (5th Cir. 2017) (quoting In re Placid Oil Co., 932 F.2d 394, 398 (5th Cir. 1991)).

         DISCUSSION

         I. The Breach of Contract Claim

         Boh Bros. argues CalFirst agreed to pay all of Boh's approved invoices when they entered into a “Supply Contract.” According to Boh Bros., the contract was formed by the string of e-mails between Hebert and Brown concerning CalFirst's instruction that the invoices be marked as “Sold to California First National Bank.” CalFirst allegedly breached this agreement by not paying Boh's third and fourth invoices. CalFirst rejects that any such contract between it and Boh Bros. ever existed.

         To understand Boh's argument that a separate contract existed between Boh Bros. and CalFirst, the Court must first explain the structure of the financing used to fund the construction of the Project. Put in the simplest terms, the parties disagree whether the financing arrangement between CalFirst and Noranda was “a typical finance lease” or “typical financing, disguised as a lease.” See In re Triplex Marine Maint., Inc., 258 B.R. 659, 673 (Bankr. E.D. Tex. 2000). This is a very common dispute in chapter 11 bankruptcy cases. Typically, the situation is that a debtor is arguing that a lease constitutes “disguised financing, ” while the creditor argues that the transaction was a “true lease.” See E. Carolyn Hochstadter Dicker & John P. Campo, FF & E and the True Lease Question: Article 2a and Accompanying Amendments to UCC Section 1-201(37), 7 Am. Bankr. Inst. L. Rev. 517, 517 (1999) (hereinafter Dicker and Campo) (“A finding that the lease is a disguised financing would favor the debtor in that the equipment would be considered property of the debtor's estate.”).

         However, this is not the typical circumstance. A bankruptcy court has already approved a global settlement-including settlement of Boh's vendor claims against Noranda for unpaid invoices as well as CalFirst's claims against Noranda for breaching its financing arrangement-and dismissed the chapter 11 proceeding.[36] In the bankruptcy proceeding, CalFirst had objected to the sale of the property subject to its financing arrangement on the ground that CalFirst enjoyed a security interest in Noranda's property.[37] CalFirst states it agreed to remove the lien in exchange for an upfront payment of $375, 000.[38] This allowed the sale of the property go forward. Now that the bankruptcy proceeding has concluded, Boh Bros. claims its rival-creditor, CalFirst, was no mere secured creditor, but a true lessor. In Boh's words, “CalFirst acquired ownership of the project.”[39]

         In support of its argument that CalFirst owned the Project and was leasing it to Noranda, Boh Bros. cites extensively to language in the Lease Agreement. To be sure, the Lease Agreement purports that CalFirst was the owner of the Project, and that the Lease Agreement constituted a true lease.[40] However, per the UCC, the contractual language is not controlling. Cal. Com. Code § 1203 (“Whether a transaction in the form of a lease creates a lease or security interest is determined by the facts of each case.”) (emphasis added). The disjunctive “or” signals that an ostensible lease may be a true lease or it may be a security interest (i.e. “disguised financing); it may not be both. Helpfully, the UCC provides a two-part analysis for determining whether a lease agreement creates a security interest.

A transaction in the form of a lease creates a security interest if the consideration that the lessee is to pay the lessor for the right to possession and use of the goods is an obligation for the term of the lease and is not subject to termination by the lessee, and:
(1) the original term of the lease is equal to or greater than the remaining economic life of the goods;
(2) the lessee is bound to renew the lease for the remaining economic life of the goods or is bound to become the owner of the goods;
(3) the lessee has an option to renew the lease for the remaining economic life of the goods for no additional consideration or for nominal additional consideration upon compliance with the lease agreement; or
(4) the lessee has an option to become the owner of the goods for no additional consideration or for nominal additional consideration upon compliance with the lease agreement.

Cal. Com. Code § 1203. Thus, if the lessee is precluded from terminating an agreement prior to the conclusion of scheduled payments-a so-called hell or high-water clause”-and one of the four prescribed conditions is met, then the purported lease is actually a security interest. See Triplex, 258 B.R. at 677.

         The Lease Agreement states that “LESSEE HEREBY WAIVES THE . . . RIGHT TO CANCEL OR TERMINATE THIS LEASE PRIOR TO EXPIRATION OF THE APPLICABLE TERM.”[41] The Lease Schedule states that upon making the final rental payment, “ONE FINAL PAYMENT OF ONE U.S. DOLLAR ($1.00) SHALL BECOME DUE, OWING AND PAYABLE BY LESSEE TO LESSOR, FOR WHICH LESSOR WILL PASS ITS TITLE IN THE PROPERTY TO THE LESSEE.”[42] Thus, Noranda, as debtor, was locked in for the full term of the agreement and-as described in subsection (4)-would become owner of the project for nominal consideration upon compliance with the Lease Agreement. Accordingly, both the conditions sufficient for a security interest are met, and despite the literal language of their financing arrangement, CalFirst was Noranda's secured creditor, not its lessor.

         Boh. Bros. attempts to paint CalFirst as the actual owner of the Project, and not a mere secured creditor because Boh Bros., as an unsecured creditor, could not adequately collect on the invoices from Noranda in the bankruptcy proceeding. Boh Bros. argues that as the true owner of the Project, CalFirst agreed to become liable to Boh Boh's invoices as a matter of contract.

         Boh's argument is complex. Boh Bros. argues that the Lease Agreement constituted a financing lease between Boh Bros. and CalFirst-a proposition the Court found to be false supra-and that for ownership of the Project to rest with CalFirst, CalFirst was required to enter into a “Supply Contract” with a “Supplier, ” which was Boh Bros. The language in the Lease Agreement allegedly giving rise to this “Supply Contract” requirement is the following: “Lessee acknowledges that it has received and approved any written ‘Supply Contract' covering the Property purchased from each Supplier . . . .”[43] The Court disagrees that this language created a requirement for CalFirst to enter into a contract with a supplier. Rather, the clause prescribes conditions in the case that one or more “Supply Contracts” exists.[44]

         Boh Bros. characterizes the quoted language as giving rise to a requirement, because a contractual requirement is necessary to explain how the e-mail exchange between Hebert and Brown could possibly be demonstrative of an intent on the part of CalFirst to obligate itself to pay all of Boh's invoices.[45] Prior to Hebert and Brown's e-mail conversation, Sanchez at Noranda instructed Alexander at Boh Bros., that Boh's invoices for the Project should be marked as “Sold to: California First National Bank” and “Ship to: Noranda Alumina, LLC.”[46] Sanchez noted in his e-mail, “Cal First will ask us for approval once they ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.