Anders Construction, Inc. v. Couvillion Group, LLC

United States District Court, E.D. Louisiana

June 26, 2015

ANDERS CONSTRUCTION, INC
v.
COUVILLION GROUP, L.L.C., ET AL., SECTION

ORDER

DANIEL E. KNOWLES, III, Magistrate Judge.

On June 24, 2015, Couvillion Group, L.L.C.'s Motion for Leave to File Third Party Complaint Against Coastal Marine Contractors, L.L.C. [Doc. #27] came on for oral hearing before the undersigned. Present were Sean McLaughlin on behalf of Anders Construction, Inc., Corey Dunbar on behalf of Couvillion Group, L.L.C., and Timothy DePaula on behalf of Tom's Welding, Inc. ("Tom's Wedling"). After the oral hearing, the Court took the motion under advisement. Having reviewed the motion, the oppositions, and the case law, the Court rules as follows.

I. Background

The complaint alleges as follows. This matter involves a dispute regarding a public works project for the dredging of Bayou St. John ("Project"). Anders Construction, Inc. ("Anders") was the general contractor on the Project. Anders subcontracted the work on the Project to Couvillion Group, L.L.C. ("Couvillion"). Couvillion hired Coastal Marine Contractors, L.L.C. ("Coastal") to perform the dredging portion of the work on the Project. During the course of discovery it was determined that Coastal improperly dredged the Project.

Couvillion paid Coastal and demanded payment from Anders. Anders refused to pay, arguing that the majority of the work performed by Coastal and Couvillion was done improperly and in the wrong location. Anders sued Couvillion and others in this Court. Couvillion then sued Anders in state court, attaching lien invoices to its petition, and then counterclaims against Anders in this Court. Answering, Anders contends that the damages from a sinking of a vessel and from finishing the Project far exceed the monies owed Couvillion for any properly-done work. All parties have sued each other in this Court.

II. The Parties' Contentions

A. The Motion

Coastal recently made demand to Couvillion for payment of a Project invoice. Because Couvillion expects litigation to ensue over the non-payment of the invoice, it seeks to file a thirdparty complaint against Coastal in this litigation.

Coastal only made demand after the deadline to add new parties. Couvillion contends that Coastal is a necessary party to this action as the dispute between it and Coastal arises from the same set of facts as the underlying lawsuit. Couvillion also argues that a separate lawsuit risks an inconsistent judgment as to the work performed by Coastal. Couvillion maintains that the thirdparty complaint will not prejudice any party.

B. The Opposition

Anders contends that the depositions of Mike Roy and Tim Couvillion have decimated Couvillion's claims. Both men admitted that the contract amount was $147, 000.00; they conceded that Couvillion and Coastal over-dredged the canal and did not follow the Project plans; and they admitted that the lien invoices that they filed in the state-court lawsuit were modified. Anders maintains that the only reason that Couvillion has filed this motion is to change the course of the lawsuit now that its claims have been debunked.

Citing Rule 16, Anders contends that Couvillion can not explain why it failed to timely move to amend when it learned that Coastal improperly dredged the canal more than 20 months ago. Anders notes that Couvillion does not attach the recent invoice from Coastal. In addition, Couvillion's complaint seeks to recover the monies that it has already paid to Coastal for the improper dredging. But Anders maintains that Couvillion has known that Coastal improperly dredged the canal for a long time.

Anders also argues that the amendment is not important. This lawsuit concerns the contract between Anders and Couvillion and the sinking of a vessel. Anders never contracted with Coastal, nor was it involved in the sinking. Anders argues that there is no risk of inconsistent judgments given that there is no evidence that the dredging work was performed properly.

Anders contends that it will be severely prejudiced if Coastal is added to this lawsuit given that Couvillion will almost certainly seek to continue the trial. Anders had to reduce its bonding capacity - given the liens filed by Couvillion in state court - and has difficulty bonding new contracts. This limits its ability to generate revenue. And the addition of Coastal will force Anders to attend additional depositions and engage in ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.